Q.8
As a business analyst, how will you handle the changes to requirements?
This is one of the most common interview question asked, you are required to play off smart and show that you are capable to handle adverse situations. This can really be the decider question for you.
Sample Answer -
First and foremost I will get signed a document by the user that states that after a point of time no changes to the requirements are accepted.
But in case if there are changes to a requirements are accepted then following steps are taken -
1. Note down the changes made to the requirements and then prioritize them
2. Go through those changes and find out the impact of them on the project.
3. Calculate the cost, timeline, and resources required to cover the impact of change requirements in the project.
4. Ensure that whether those changes affect or create gaps to functional design documents, testing or coding